June 2018 Construction Update

Construction Progress Site Work Installation of new curb lines and binder course along Burlington and the area between the buildings. Relocation of the traffic signal at the corner of Main Street and Burlington Road. Commence of hardscape elements including sidewalks and pavers. Commence roofing and landscaping of terrace area. West Building MEP rough in, including…

Read More

May 2018 Construction Update

Construction Progress Site Work Installation of new curb lines and binder course to the north of the property, as well as preparation for portions of the Burlington Road curb line. Relocation of the traffic signal at the corner of Main Street and Burlington Road. Removal of old watermain connections across Main Street near the fountain.…

Read More

April 2018 Construction Update

Construction Progress Site Work Completion of the water main work along Burlington and in-between the two buildings. Completion of existing curb and asphalt demolition in preparation for new curbs and binder course along Burlington. West Building MEP rough in, including electrical conduits and panels, fire protection lines, return and supply ductwork, and plumbing lines, to…

Read More

March 2018 Construction Update

Construction Progress Site Work Completion of the water main work along Burlington and in-between the two buildings. Site work to commence in spring 2018. West Building MEP rough in, including electrical conduits and panels, fire protection lines, return and supply ductwork, and plumbing lines, to continue on all levels. Layout and installation of exterior panels…

Read More

February 2018 Construction Update

Construction Progress Site Work Completion of the sanitary, storm and water main work along Burlington and in-between the two buildings. Commence site work in spring 2018. West Building Plumbing and electrical rough in to continue on lower level and level 1. Layout of exterior panels for level 2 to continue. Completion of ComEd transformer installation.…

Read More

January 2018 Construction Update

Construction Progress Site Work Completion of the sanitary, storm and water main work along Burlington and Main and in-between the two buildings. Commence site work in spring 2018. West Building Completion of slab on grade in the retail areas on level 1. Plumbing and electrical rough in to continue on lower level and level 1.…

Read More

December 2017 Construction Update

Construction Progress Site Work Completion of the sanitary, storm and water main work along Burlington and Main. Commence relocation of traffic signal at the Burlington/Main Street corner. West Building Installation of the concrete toppings in the garage, as well as slab on grade of the lower level. Plumbing and electrical rough in to continue on…

Read More

November 2017 Construction Update

Construction Progress Site Work Installation of the sanitary, storm and water main work within the street will continue, and is targeted for completion in mid-November. Commence relocation of traffic signal at the Burlington/Main Street corner. West Building    Completion of the last bay of precast structure on the south side of the building. Installation of structural…

Read More

October 2017 Construction Update

Construction Progress Site Work Installation of the sanitary, storm and water main will continue, and is scheduled for completion in mid-November. Work will begin on perimeter damproofing. West Building Completion of the last bay of precast structure on the south side of the building. Installation of the concrete toppings in the garage and on top…

Read More

August 2017 Construction Update

Construction Progress Site Work Installation of new construction trailer, maintenance of existing perimeter fencing, overall site cleanup, removal of trash and weeds, patching of sidewalk on Main Street. Installation of various safety control measures and 24 hour lighting in both buildings. Reestablishments of gates. Underground stormwater piping and catch basins were installed between the buildings…

Read More