December 2017 Construction Update

  |     |   Uncategorized

Construction Progress

Site Work

Completion of the sanitary, storm and water main work along Burlington and Main. Commence relocation of traffic signal at the Burlington/Main Street corner.

West Building

Installation of the concrete toppings in the garage, as well as slab on grade of the lower level. Plumbing and electrical rough in to continue on lower level and level 1. Layout of exterior panels for level 2 to commence. Masonry enclosure of stair tower and elevator shafts to commence.

East Building

Continued progress of wall panel and floor truss installation and masonry enclosure of stair towers and elevator shafts. MEP rough in to continue on lower level, level 1 and level 2. Commence installation of exterior windows on residential levels.

More Information

We look forward to working with the community to bring this new development to completion! For general questions or comments, please contact us at marqonmain.com.                           