March 2018 Construction Update

  |     |   Uncategorized

Construction Progress

Site Work

Completion of the water main work along Burlington and in-between the two buildings. Site work to commence in spring 2018.

West Building

MEP rough in, including electrical conduits and panels, fire protection lines, return and supply ductwork, and plumbing lines, to continue on all levels. Layout and installation of exterior panels and windows for levels 2 and 3 to continue. Installation of structural steel at level 2 and installation of the balance of the slab on grade in future retail spaces.

East Building

Commencement of roofing membrane installation, cast stone and brick installation, siding and panel installation. MEP rough in, including electrical conduits and panels, fire protection lines, return and supply ductwork, and plumbing lines, to continue on all levels. Installation of slab on grade in future retail space. Commence installation of insulation and drywall at units on level 2. Continued installation of exterior patio sliders and doors on residential levels.

More Information

We look forward to working with the community to bring this new development to completion! For general questions or comments, please contact us at marqonmain.com.