April 2018 Construction Update

  |     |   Uncategorized

Construction Progress

Site Work

Completion of the water main work along Burlington and in-between the two buildings. Completion of existing curb and asphalt demolition in preparation for new curbs and binder course along Burlington.

West Building

MEP rough in, including electrical conduits and panels, fire protection lines, return and supply ductwork, and plumbing lines, to continue on all levels. Layout and installation of exterior panels and windows for levels 2 and 3 to continue.

East Building

Completion of upper roof membrane. Continued installation of cast stone and brick installation. Commencement of siding and panel installation. MEP rough in, including electrical conduits and panels, fire protection lines, return and supply ductwork, and plumbing lines, to continue on all levels. Commence installation of insulation and drywall at units on level 2. Continued installation of light weight concrete topping on levels 3, 4, and 5. Continued installation of exterior patio sliders and doors on residential levels.

More Information

We look forward to working with the community to bring this new development to completion! For general questions or comments, please contact us at marqonmain.com.             

 

Leave a reply

required

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>