June 2018 Construction Update

  |     |   Uncategorized

Construction Progress

Site Work

Installation of new curb lines and binder course along Burlington and the area between the buildings. Relocation of the traffic signal at the corner of Main Street and Burlington Road. Commence of hardscape elements including sidewalks and pavers. Commence roofing and landscaping of terrace area.

West Building

MEP rough in, including electrical conduits and panels, fire protection lines, return and supply ductwork, and plumbing lines, to continue on all levels. Continued progress of interior and exterior wall panels on all levels. Completion of framing and exterior sheathing for the ground level retail areas, including interior framing for these areas. Commence installation of cast stone and the ground level and patio slider doors. 

East Building

Continued installation of siding, panels and roof level cornice. MEP rough in, including electrical conduits and panels, fire protection lines, return and supply ductwork, and plumbing lines, to continue on all levels. Commence installation of the elevator system. Continued installation of insulation and drywall on levels 2, 3 and 4. Installation of projected balconies. Continued installation of interior finishes including cabinets, trim, paint and flooring.

More Information

We look forward to working with the community to bring this new development to completion! For general questions or comments, please contact us at marqonmain.com.