November 2018 Construction Update

  |     |   Uncategorized

Construction Progress

Site Work

Paving operations along Burlington Avenue. Sidewalk installation at west building. Hardscape and paver installation at plaza area between both buildings.

West Building

MEP rough in, including electrical conduits and panels, fire protection lines, return and supply ductwork, and plumbing lines, to continue on all levels. Continued roofing installation for the level 2 courtyard and main roof areas. Continued installation of cast stone and masonry. Continued installation of sliding doors and windows. Commence installation of exterior siding and trim. Continued installation of drywall insulation on levels 2 and 3, as well as electrical closets throughout the building.

East Building

We now have certificates of occupancy from the Village for all levels of the building. Interior and exterior punch list items are in progress.

More Information

We look forward to working with the community to bring this new development to completion! For general questions or comments, please contact us at marqonmain.com.

Leave a reply

required

<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>