February 2018 Construction Update

Construction Progress Site Work Completion of the sanitary, storm and water main work along Burlington and in-between the two buildings. Commence site work in spring 2018. West Building Plumbing and electrical rough in to continue on lower level and level 1. Layout of exterior panels for level 2 to continue. Completion of ComEd transformer installation.…

Read More

January 2018 Construction Update

Construction Progress Site Work Completion of the sanitary, storm and water main work along Burlington and Main and in-between the two buildings. Commence site work in spring 2018. West Building Completion of slab on grade in the retail areas on level 1. Plumbing and electrical rough in to continue on lower level and level 1.…

Read More

December 2017 Construction Update

Construction Progress Site Work Completion of the sanitary, storm and water main work along Burlington and Main. Commence relocation of traffic signal at the Burlington/Main Street corner. West Building Installation of the concrete toppings in the garage, as well as slab on grade of the lower level. Plumbing and electrical rough in to continue on…

Read More

November 2017 Construction Update

Construction Progress Site Work Installation of the sanitary, storm and water main work within the street will continue, and is targeted for completion in mid-November. Commence relocation of traffic signal at the Burlington/Main Street corner. West Building    Completion of the last bay of precast structure on the south side of the building. Installation of structural…

Read More

October 2017 Construction Update

Construction Progress Site Work Installation of the sanitary, storm and water main will continue, and is scheduled for completion in mid-November. Work will begin on perimeter damproofing. West Building Completion of the last bay of precast structure on the south side of the building. Installation of the concrete toppings in the garage and on top…

Read More

August 2017 Construction Update

Construction Progress Site Work Installation of new construction trailer, maintenance of existing perimeter fencing, overall site cleanup, removal of trash and weeds, patching of sidewalk on Main Street. Installation of various safety control measures and 24 hour lighting in both buildings. Reestablishments of gates. Underground stormwater piping and catch basins were installed between the buildings…

Read More

January 2017 Construction Update

Progress on the mixed-use residential and retail development currently under construction in Downtown Lisle should be even more evident in the coming weeks, as pre-cast columns and walls begin to go up at the site. With much of the foundation and preliminary site work complete, pre-cast concrete columns and panels will take the project rapidly…

Read More

Marquette Companies Join Lisle Village Officials in Groundbreaking for Downtown Development

Officials from developers Marquette Companies joined Lisle Mayor Joe Broda, Members of the Village Board of Trustees, Village Staff and members of the Lisle Chamber of Commerce on Tuesday in turning shovels to begin construction on the development on the Old Village Hall site in Downtown Lisle. Construction is expected to be complete in 2017.…

Read More